Reconstruction of Aprons in the Vicinity of Hangars 1 through 5, North Field

The work on this project consisted of reconstructing portions of aprons including existing pavement, removing existing utilities, preparing sub grade, replacing storm drain lines, installing water lines, reconstructing pavement, installing new Portland cement concrete pavement, installing pavement striping and markings, and performing all associated work.

Location: Oakland International Airport
Oakland, California
Start Date: September 2005
Completion Date: November 2006, 400 calendar days
Contract Value: $13,057,210
Owner: Port of Oakland
The Board of Port Commissioners
Contract No. 2005-06-A1
Engineer: Port of Oakland